Industrial Avenue Waterline Replacement

Project Overviewvicinity map

A utility improvements project on E. Industrial Drive from approximately Steve’s Boulevard to N. Caden Court.  The improvements consist of replacing approximately 2,050 linear feet of 16” ductile iron waterline pipe, associated paving for the waterline trench, removal and replacement of curb, gutter and valley gutter.

  • Cost: $589,819.00
  • Location: Industrial Drive from Steve’s Blvd to Caden Court
  • Project Manager: Mac McNamara
  • Timeline: July 2020 – November 2020
  • Contractor: Revolution Industrial 

_______________________________________________________________________________________________________________

2020 Periodic Updates

August:

  • Traffic Control Plans are in for review.  Traffic impacts will involve lane shifts to accommodate the new waterline in Industrial Dr and mostly likely a brief full closure of the Steve’s Boulevard and Industrial Drive intersection to tie the old main into the new main. 
  • Project start slated for August 10th.

July:

  • Contract with Revolution Industrial approved at June 16th City Council meeting.
  • Pre-Construction meeting will be held on July 15th. 
  • Project start slated for August 3rd.