Project Overview
Approximately 3,300 ft of new waterline, water services, fire hydrants, and pavement reconstruction. The existing waterlines in this area range from 58 to more than 90 years old. The City intends to replace the water infrastructure and pavement on: S Walnut St. from Santa Fe Avenue to Coconino Avenue; S Sycamore St. from Santa Fe Avenue to Grand Canyon Avenue; S Spring St. from Montvale Avenue to Grand Canyon Avenue; W Summit Avenue from Santa Fe Avenue to end; and W Santa Fe Avenue from Walnut St. to Thorpe Road Waterline only will be installed on W Montvale Avenue from Santa Fe Avenue, to end. This project is part of the City's ongoing aging water infrastructure replacement program.

Cost: $1,359,657
Location: Summit Avenue and Spring Street
Project Manager: Jeremy DeGeyter
Timeline: Construction Start: July 2020. Project Completion: Spring/Summer 2021
Contractor: Overley's