Summit Avenue Water Main Replacement

Project Overview

Approximately 3,300 ft of new waterline, water services, fire hydrants, and pavement reconstruction. The existing waterlines in this area range from 58 to more than 90 years old. The City intends to replace the water infrastructure and pavement on: S Walnut St. from Santa Fe Avenue to Coconino Avenue; S Sycamore St. from Santa Fe Avenue to Grand Canyon Avenue; S Spring St. from Montvale Avenue to Grand Canyon Avenue; W Summit Avenue from Santa Fe Avenue to end; and W Santa Fe Avenue from Walnut St. to Thorpe Road Waterline only will be installed on W Montvale Avenue from Santa Fe Avenue, to end. This project is part of the City's ongoing aging water infrastructure replacement program.

summit

Cost: $1,359,657

Location: Summit Avenue and Spring Street

Project Manager: Jeremy DeGeyter

Timeline: Construction Start: July 2020. Project Completion: Spring/Summer 2021

Contractor: Overley's


2020 Periodic UpdatesVicinity map

October 

  • Water tie-ins on Walnut St., Sycamore St. and Summit Ave. completed. 
  • Pavement removal underway on Walnut St. and Sycamore St. 
  • Waterline work has begun on Santa Fe Ave. 
  • Select replacement of sidewalk panels and curb and gutter. 
  • Construction yard is set up on Coconino Avenue and sharing the overall space with the Humphreys Street ADOT project.

August

  • Construction is underway, beginning with Phase I on Walnut St.
  • Work to begin on Sycamore St. next.
  • Construction yard is set up on Coconino Avenue and sharing the overall space with the Humphreys Widening ADOT project.

July

  • Contract with Overley's approved at June 2nd City Council meeting.
  • Pre-Construction meeting held June 25th.
  • Project started on July 6th.
  • Project Notification flyers sent to neighborhood.