Route 66 Waterline Extension

Project Overview

A utility improvements project that extends the 12” ductile iron waterline approximately 2,450 linear feet from approximately the intersection of Test Dr. and Rt. 66 to the intersection of El Paso Flagstaff Rd. The waterline extension continues north, up El Paso Flagstaff Road towards the Wildcat Hill Wastewater Treatment plant, with approximately 1,600 linear feet of new 8” ductile iron waterline. The project also calls for a repaving of El Paso Flagstaff Road for the extents of the waterline extension. This project is part of the Aging Infrastructure Replacement Program. 

  • Cost: $1,326,123
  • Location: E Route 66 and N El Paso Flagstaff Rd
  • Project Manager: Mac McNamara
  • Timeline: Fall 2021 - July 2022
  • Contractor: Scholz Contracting, LLC
Installation of the Route 66 Waterline
Project Map - RT66 waterline

2022 Project Updates:

  • May
    • The entire 8- inch of ductile iron waterline within El Paso Flagstaff Rd, approximately 1,600 linear feet, was constructed in April.
    • Crews have begun on the 12-inch ductile iron waterline extension that runs along E Rt 66 that is approximately 2,500 linear feet.
    • Paving of El Paso Flagstaff Rd is currently scheduled for late May.
  • April
    • A Notice to Proceed has been issued for March 14, 2022. Tentative project completion is for September 2022.
    • On the week of March 21 our Contractor, Scholz Contracting, mobilized and installed SWPPP.
    • On the week of March 28 Scholz Contracting began installation of the 8” ductile iron waterline that runs the length of El Paso Flagstaff Rd.
  • March
    • A Notice to Proceed has been issued for March 14, 2022. Tentative project completion is for September 2022.