Industrial Drive Waterline Replacement

Project OverviewDJI_0026 (2)

A utility improvements project on E Industrial Drive from approximately Steve's Boulevard to N Caden Court. The improvements consist of replacing approximately 2,050 linear feet of 16" ductile iron waterline pipe, associated paving for the waterline trench, removal and replacement of curb, gutter and valley gutter.

  • Cost: $589,819
  • Location: Industrial Drive from Steve's Boulevard to Caden Court
  • Project Manager: Mac McNamara
  • Timeline: July 2020 - November 2020
  • Contractor: Revolution Industrial

Completed view of Industrial Drive 

2020 Periodic Updates

December

  • The project is substantially complete. Striping, valve adjustments and stabilization of disturbed soils will need to be completed to finish the project.

October:

  • The waterline system was pressure tested with passing results this week. October photo
  • The waterline system will be chlorinated for disinfection end of week and then paving will commence early next week, 10/12. 
  • Traffic control is in place with a south lane shift on Industrial Dr. from Caden Court to Walgreens St.

August:

  • Traffic Control Plans are in for review. Traffic impacts will involve lane shifts to accommodate the new waterline in Industrial Dr and mostly likely a brief full closure of the Steve's Boulevard and Industrial Drive intersection to tie the old main into the new main.
  • Project start slated for August 10th.

July:

  • Contract with Revolution Industrial approved at June 16th City Council meeting.
  • Pre-Construction meeting will be held on July 15th.
  • Project start slated for August 3rd.



Crews installing last legs of waterline before the tie ins at the intersection.